Brighton - Work to replace McKain’s Bridge over the Skunk River on Dogwood Avenue (W21) in Washington County will begin Monday, Nov. 16. The bridge is more than 75 years old and in major need of replacement. According to the Washington County Road Department, the county has spent the past 25 years seeking funding to replace the bridge...

This item is available in full to subscribers.

Please log in to continue

E-mail
Password
Log in

Replacement set for 75-year-old McKain’s Bridge

McKain’s Bridge in Washington County to be replaced

Posted

Brighton

Work to replace McKain’s Bridge over the Skunk River on Dogwood Avenue (W21) in Washington County will begin Monday, Nov. 16. The bridge is more than 75 years old and in major need of replacement.

According to the Washington County Road Department, the county has spent the past 25 years seeking funding to replace the bridge.

The project is supported by a $38.6 million federal Bridge Investment Program (BIP) grant. Washington County led the effort to secure the grant and is one of six counties receiving funding. The grant will cover approximately 80% of the project’s cost, with the remaining 20% coming from Washington County’s Farm to Market funds.

Washington County Engineer Jacob Thorius expressed his gratitude for the funding.

“This project was simply too expensive for the County to tackle on its own. The BIP grant finally makes this long-needed replacement possible. We are thankful to the Federal Highway Administration for the grant.”

The current bridge is 50 feet long. Its replacement will be an 800-foot-long, 30-foot-wide concrete beam bridge.

In addition to its age, the existing bridge is narrow, making it difficult for vehicles to pass each other. Its condition is also approaching the point at which a weight restriction would be needed.

According to the Washington County Road Department, the new bridge and road improvements will provide a safer, more reliable crossing for local residents, agricultural traffic and emergency services. The improvements will also help reduce the frequent flooding that has affected the roadway.

The road will remain open during the initial phase of construction, although traffic may be reduced from two lanes to one as work continues.

Bridge construction is expected to continue through the summer of 2027, followed by roadway grading later that year. Paving of the new Dogwood Avenue alignment is expected to begin in 2028.

The project will span 1,251 feet along W21. Peterson Contractors, Inc., of Reinbeck, will handle the work.

For questions about the project, contact the Washington County Road Department at 319-653-7731 or email Thorius at jthorius@washingtoncounty.iowa.gov.